HCLT West End Gardens Development - Latest Updates

page1image24446592

 

West End Gardens, Haddenham –

Update 24/11/19. 

 

After getting all the pre-start planning conditions signed off, we commenced in carrying out the remedial works to the site entrance to ensure that all vehicle and pedestrian movements could be carried out in a safe manner. This also included installing tree protection to the two trees on the parish land directly in front of the site. (We are having a slight delay in getting the overhead power diverted underground but this isn’t anything unusual where Utility Companies are involved and we are pushing hard to get this resolved.)

With regards to the main site the initial operation was to carry out a full site strip of topsoil which has been carried out by our groundworker and all this material has been stored on site to minimise any lorry movements through the village. We envisage that this topsoil will be reused on the project when making up the soft landscaped areas.

One of the next operations was to get all the infrastructure works in place and over the past few weeks we have been installing all the mains drainage that runs through the site and have been setting out for the access roads and foundations. This has been progressing well despite all the recent rain.

You may have seen that we have commenced the access road from West End into the site which we hope to have complete, minus the topcoat of tarmac, by mid-January next year. During this operation we will be looking to minimise any disruption to the access for Hardwicke Fields and the track that runs adjacent to the site, and are confident we will be able to keep these open but can we please ask you to be patient if any disruption does occur. (We will strive to give the major users of both routes as much notice as possible if their access is going to be hindered at any point and I’m sure our onsite team will try and resolve any issues that may occur.)

Whilst this is happening, we have programmed to commence the foundations in tandem with the access road works, again with a view to start the superstructure works in January 2020 when people will start to see the properties coming out of the ground. (It is sometimes hard to envisage progress at the minute due to all the works that have taken place being under the ground.)

From January, we will be looking to increase our labour force on site and in turn install our temporary site offices for our Site Manager, Paul Elliott, and his team to run the project as smoothly as possible for us and the residents of Haddenham.

 

 

 

 

 

Update 31/10/19

 

Since planning permission was granted in 2018, things have been progressing well on site, including the completion of a second archaeological dig in November 2018. The initial report found evidence of an early Roman  farmstead on part of the site.

The second dig provided a unique opportunity for local residents and children at the Robert Arkenstall Primary School to visit the site to meet with the team of archaeologists. They enjoyed a special day out looking at fragments of animal bone and ancient pottery and learning more about their local village history.

In January 2019, we received some fantastic news that our bid to the Homes England Community Housing fund was successful and have been awarded a grant payment of just over £42,000. This is a great achievement for the CLT and will see vital funds go towards the project. With the help from EC Community Housing we have also been interviewing ethical banks to secure the additional funding needed to purchase the affordable homes when they are completed.

 

What's Next?

Work began on the enabling works in August 2019 to get the site ready for construction of the site access road and diversions/connections of utility services. Groundworks  are proceeding throughout the Autumn/Winter with construction of the first houses underway in early 2020. The first homes in the development are expected to be ready for occupation in late summer 2020, including the first CLT owned affordable homes. During this time we will be working closely with Palace Green Homes to try to keep disruption from construction activity to a minimum and will be keeping the neighboring residents informed of our progress and proposed works.

 

We are located at:

 

Arkenstall Centre
c/o The Library,

Haddenham

CB6 3XD

Contact us today!

If you have any queries or wish to make an appointment, please contact us:

 

 

 

admin@haddenhamclt.org.uk

 

Or via our Contact Us page

 

Get social with us.

Print Print | Sitemap
© Chris Ray